Mon 26 OctKestrel Yard, Marlbridge

Demoweek 1 of 4

Items

IRS line · Concrete Frame and Core

FR-04

Slab edge details and cast-in items, levels 04–08

OpenDue 30/11Held by PellamDrawings: 0 of 2 issued (from Asite, synced 09:14)

Who is holding it up

Pellam, Structural engineer

“Pellam Structures”
Information Required Schedule, row 10, Required From · 19/10

Knock-on effects

No other item is held up by it.

Linked items

No linked items.

Chases drafted

No chase drafted for this item.

Drawings on Asite

0 of 2 issued · read-only, synced 09:14

  • KTY-PEL-ZZ-ZZ-DR-S-1400

    Slab edge details, levels 04 to 08

    Planned, nothing issued

  • KTY-PEL-ZZ-ZZ-SH-S-1401

    Cast-in items schedule, levels 04 to 08

    Planned, nothing issued

Timeline

Nothing has been linked to this item yet.

Actions and chases

No action in the minutes and no chase sent on this item.