Mon 26 OctKestrel Yard, Marlbridge

Demoweek 1 of 4

Hi Tom

Needs you

5

updates to confirm

Review updates

1

possible change for the change register

Review possible changes

12

chases drafted

Review chases

12 done automatically since the last import

Packages

  • Façade

    14 days late

    FA-02 due 12/10

    Held by Farrow Lune, Architect

    Details
  • Mechanical and Electrical

    Due today

    ME-02 due 26/10

    Held by Northvane, MEP consultant

    Details
  • Structural Steelwork

    Due in 7 days

    ST-03 due 02/11

    Linked RFI-014, status “Awaiting MEP info”

    Depends on ME-02, status “O/S”

    Held by Northvane, MEP consultant

    Details

4 packages on track

See all 7 packages

Held up by another party

Due in the next 14 days with an input still outstanding

  • ST-03 · Steelwork connection details – primary beams to core

    • Linked RFI-014, status “Awaiting MEP info”
    • Depends on ME-02, status “O/S”
    Due in 7 days

    Due 02/11

Overdue items per party

  • Farrow Lune, Architect

    4 overdue

    Details

    Oldest RFI-012, issued 35 days ago

  • Northvane, MEP consultant

    3 overdue

    Details

    Oldest RFI-020, issued 25 days ago

  • Pellam, Structural engineer

    1 overdue

    Details

    Oldest RFI-018, issued 27 days ago