Imported from RFI Register.xlsx on 19/10/2026·31 rows
Download the original file1 column hidden in your file: Location
Select a cell to see where its value came from. Double-click it, or start typing, to edit it.
Halbrook Construction Ltd
Kestrel Yard, Marlbridge – Request for Information Register
| A | B | C | E | F | G | H | I | J | |
|---|---|---|---|---|---|---|---|---|---|
| Row in your file | RFI No: | Date Issued: | Issued to / Action: | Package | Information Requested: | Date Information Required: | Response | Date Information Received: | Status |
| 5 | RFI-001 | 01/09/2026 | Pellam Structures | Frame | Confirm concrete grade for core walls below level 01 – drawings show C32/40 and C40/50. | 08/09/2026 | C40/50 throughout core. Drawing to be revised at next issue. | 04/09/2026 | Closed |
| 6 | RFI-002 | 01/09/2026 | Arch – DO | Fit-out | Floor-to-ceiling height in retail units – 3.6 m or 3.8 m? | 11/09/2026 | 3.8 m clear to underside of services zone. | 10/09/2026 | CLOSED |
| 7 | RFI-003 | 03/09/2026 | Northvane | M&E | Confirm weight of roof plant for frame design. | 17/09/2026 | See RF-03 loadings schedule. | 16/09/2026 | Closed |
| 8 | RFI-004 | 04/09/2026 | SE / Arch | Steelwork | Edge beam depth conflicts with window head height on elevation A. Please coordinate. | 18/09/2026 | Beam reduced to 356 UB. Window head unchanged. | 21/09/2026 | Closed |
| 9 | RFI-005 | 08/09/2026 | FLA | Roof | Upstand height at roof outlets – 150 mm or 75 mm? | 15/09/2026 | Answered by email 18/09 – 150 mm upstand, see detail KTY-FLA-ZZ-R1-DR-A-4104. | 18/09/2026 | Blank |
| 10 | RFI-006 | 08/09/2026 | Northvane (RP) | M&E | Incoming water main position – drawings disagree. | 22/09/2026 | Revised layout ME-03 (KTY-NVE-ZZ-00-DR-MEP-6301 C01). | 22/09/2026 | Closed - see email 12/10 |
| 11 | RFI-007 | 10/09/2026 | Velmore Façades | Façade | Confirm curtain wall mullion spacing to suit flat layouts. | 24/09/2026 | 1500 mm typical; 1200 mm at stair core. | 23/09/2026 | Answered |
| 12 | RFI-008 | 11/09/2026 | Pellam Structures | Frame | Transfer slab thickness – 350 or 400 mm? | 18/09/2026 | Superseded by RFI-011. | Superseded | |
| 13 | RFI-009 | 14/09/2026 | Arch – LB | Fit-out | Bathroom pod or traditional build for type D flats? | 28/09/2026 | Traditional build – client preference. | 25/09/2026 | Closed |
| 14 | RFI-010 | 15/09/2026 | Corvane Steel | Steel | Confirm splice positions for columns C2–C6 to suit delivery lengths. | 29/09/2026 | Splices at level 03 and 06. | 28/09/2026 | Resp rec'd |
| 15 | RFI-011 | 17/09/2026 | Pellam Structures | Frame | Transfer slab thickness and punching shear reinforcement at core. | 01/10/2026 | 400 mm with shear studs – see FR-02 (KTY-PEL-ZZ-ZZ-DR-S-1201 C02). | 30/09/2026 | Closed |
| 16 | RFI-012 | 21/09/2026 | Farrow Lune | Façade | Soldier course above shopfronts – drawings show brick blend A on a precast concrete boot. Confirm support detail and brick type. | 05/10/2026 | With Architect | ||
| 17 | RFI-013 | 22/09/2026 | Northvane | M&E | Smoke vent shaft size – does it need to grow for the revised flat layout? | 06/10/2026 | No change. Existing 1.0 m² shaft is adequate. | 02/10/2026 | Closed |
| 18 | RFI-014 | 07/10/2026 | Pellam Structures / Northvane | Steelwork | Primary beams at the core: confirm the size and position of penetrations for the MEP risers so the connection details can be finalised (IRS ST-03). | 21/10/2026 | SE holding – riser sizes needed from Northvane before beam openings can be confirmed. ME 14/10 | Awaiting MEP info | |
| 19 | RFI-015 | 24/09/2026 | Arch | Balconies | Balcony soffit finish – render or cladding board? | 08/10/2026 | Cladding board, colour to match window frames. | 07/10/2026 | Closed |
| 20 | RFI-016 | 25/09/2026 | Client – HD | Fit-out | Is retail unit 2 still to be let as a café? Affects extract route. | 09/10/2026 | unit 2 will be let as a café, so it will need a kitchen extract | Answered | |
| 21 | RFI-017 | 28/09/2026 | Pellam | Steelwork | Plant support frame – steel or concrete upstands? | 12/10/2026 | Steel frame on concrete plinths. | 09/10/2026 | Closed |
| 22 | RFI-018 | 29/09/2026 | SE | Frame | Stair landing connection to core wall – cast-in plate or resin anchors? | 13/10/2026 | Awaiting SE | ||
| 24 | RFI-019 | 30/09/2026 | Velmore | Façade | Cavity barrier positions at floor slabs – Velmore detail differs from architect’s. | 14/10/2026 | Velmore detail accepted by FLA. | 14/10/2026 | Closed |
| 25 | RFI-020 | 01/10/2026 | Northvane | MEP | MVHR unit location in type B flats clashes with storage cupboard. | 15/10/2026 | O/S | ||
| 26 | RFI-021 | 02/10/2026 | FLA | Fit-out | Lobby floor finish – porcelain tile or terrazzo? | TBC | open | ||
| 27 | RFI-022 | 05/10/2026 | Pellam Structures | Balconies | Thermal break product – is the specified one still acceptable at 2.1 m cantilever? | 19/10/2026 | Confirmed: the heavier unit at all 2.1 m cantilevers | Answered | |
| 28 | RFI-023 | 06/10/2026 | Arch – DO | Roof | Roof access hatch or stair to plant area? | 20/10/2026 | Open | ||
| 29 | RFI-024 | 07/10/2026 | Farrow Lune | Façade | Window reveal depth – 100 or 215 mm? | 21/10/2026 | With Architect | ||
| 30 | RFI-025 | 08/10/2026 | Corvane Steel | Steelwork | Can the 610 UB at C1–C2 be delivered in one length (14.2 m)? | ASAP | Yes – escorted load, 2 weeks' notice. | 12/10/2026 | Resp rec'd |
| 31 | RFI-026 | 09/10/2026 | Northvane / Pellam | M&E | Drainage run under core – sleeve through pile cap or reroute? | 23/10/2026 | O/S | ||
| 32 | RFI-027 | 12/10/2026 | FLA | Fit-out | Flat entrance doors: confirm fire rating and whether vision panels are needed. | 26/10/2026 | Awaiting response | ||
| 33 | RFI-028 | 13/10/2026 | Arch – LB | Façade | Brick bond at parapet – stretcher bond as drawn, or Flemish bond to match ground floor? | 27/10/2026 | With Architect | ||
| 34 | RFI-029 | 14/10/2026 | Pellam | Steelwork | Secondary beam notch at gridline D4 – confirm acceptable. | 28/10/2026 | Awaiting SE | ||
| 35 | RFI-030 | 15/10/2026 | Client | Fit-out | Penthouse kitchen upgrade – proceed with standard spec until client decision? | 29/10/2026 | Awaiting response | ||
| 36 | RFI-031 | 16/10/2026 | Northvane (CD) | M&E | Riser R1 access panels – fire rating and size? | 30/10/2026 | O/S |