RFI · Structural Steelwork

RFI-010

Confirm splice positions for columns C2–C6 to suit delivery lengths.

AnsweredDue 29/09Held by Halbrook

Updates to confirm

1 waiting for you

Dates and statuses in your trackers change only when you confirm.

  • Status to Closed

    “Splices at level 03 and 06.”
    RFI Register, row 14, Response · 19/10

Who is holding it up

Halbrook, Contractor

The answer is in, to review and close

“Splices at level 03 and 06.”
RFI Register, row 14, Response · 19/10

Knock-on effects

No other item is held up by it.

Linked items

CR-012 Column splices moved to levels 03 and 06

Names this item in its Source

“RFI-010”
Change Control Register, row 17, Source · 19/10

Chases drafted

No chase drafted for this item.

Timeline

October 2026

Actions and chases

No action in the minutes and no chase sent on this item.