RFI · Structural Steelwork
RFI-010
Confirm splice positions for columns C2–C6 to suit delivery lengths.
AnsweredDue 29/09Held by Halbrook
Updates to confirm
1 waiting for you
Dates and statuses in your trackers change only when you confirm.
Status to Closed
“Splices at level 03 and 06.”
RFI Register, row 14, Response · 19/10
Who is holding it up
Halbrook, Contractor
The answer is in, to review and close
“Splices at level 03 and 06.”
Knock-on effects
No other item is held up by it.
Linked items
CR-012 Column splices moved to levels 03 and 06
Names this item in its Source
“RFI-010”
Chases drafted
No chase drafted for this item.
Timeline
October 2026
Actions and chases
No action in the minutes and no chase sent on this item.