RFI · Retail Shell and Residential Fit-out

RFI-016

Is retail unit 2 still to be let as a café? Affects extract route.

AnsweredDue 09/10Held by Halbrook

Possible changes for the change register

1 waiting for you

Each one goes into your change register only when you add it.

  • Possible change

    “unit 2 will be let as a café, so it will need a kitchen extract”
    Helen Doyle, Wrenfield · 22/10

Who is holding it up

Halbrook, Contractor

The answer is in, to review and close

“unit 2 will be let as a café, so it will need a kitchen extract”
Helen Doyle, Wrenfield · 22/10

Knock-on effects

No other item is held up by it.

Parent IRS line

Not linked to an IRS line.

Chases drafted

No chase drafted for this item.

Timeline

October 2026

Actions and chases

  • Action · DTM 07, point 5.1 · Wrenfield · new · due 21/10

    “Use of retail unit 2 (RFI-016): Wrenfield to confirm whether it will be let as a café.”