RFI · Structural Steelwork

RFI-025

Can the 610 UB at C1–C2 be delivered in one length (14.2 m)?

AnsweredHeld by Halbrook

Updates to confirm

1 waiting for you

Dates and statuses in your trackers change only when you confirm.

  • Status to Closed

    “Yes – escorted load, 2 weeks' notice.”
    RFI Register, row 30, Response · 19/10

Who is holding it up

Halbrook, Contractor

The answer is in, to review and close

“Yes – escorted load, 2 weeks' notice.”
RFI Register, row 30, Response · 19/10

Knock-on effects

No other item is held up by it.

Parent IRS line

Not linked to an IRS line.

Chases drafted

No chase drafted for this item.

Timeline

October 2026

Actions and chases

No action in the minutes and no chase sent on this item.