IRS line · Structural Steelwork
ST-04
Fabrication drawings for approval
OpenDue 30/11Held by CorvaneDrawings: 0 of 2 issued (from Asite, synced 09:14)
Who is holding it up
Corvane, Steelwork subcontractor
“Corvane Steel”
Knock-on effects
No other item is held up by it.
Linked items
ST-03 Steelwork connection details – primary beams to core
Due in 7 days· due 02/11·Depends on
“Corvane can't start until ST-03 is issued”
Chases drafted
No chase drafted for this item.
Drawings on Asite
0 of 2 issued · read-only, synced 09:14
KTY-COR-ZZ-ZZ-DR-X-2401
Fabrication drawings, primary beams
Planned, nothing issued
KTY-COR-ZZ-ZZ-DR-X-2402
Fabrication drawings, connections to core
Planned, nothing issued
Timeline
October 2026
Actions and chases
No action in the minutes and no chase sent on this item.