IRS line · Structural Steelwork
ST-03
Steelwork connection details – primary beams to core
OpenDue in 7 daysDue 02/11Held by NorthvaneDrawings: 0 of 3 issued (from Asite, synced 09:14)
Who is holding it up
Northvane, MEP consultant
Through RFI-014, which is waiting on them
“We'll have the riser sizes to Pellam by Fri 30/10.”
Knock-on effects
ST-04 Fabrication drawings for approval
Linked items
RFI-014 Primary beams at the core: confirm the size and position of penetrations for the MEP risers so the connection details can be finalised (IRS ST-03).
5 days late· due 21/10·Linked RFI
ME-02 Riser sizes and builders' work in connection (BWIC)
Due today· due 26/10·Depends on
“Needed by Pellam for ST-03 connections”
Chases drafted
To Raj Patel, Northvane
In the chase for RFI-014
RFI-014 / ST-03 / ME-02: thanks for confirming the riser sizes will be with Pellam by Fri 30/10. Mark needs them to finalise the steel connections at the core, due on the IRS on 02/11. Your own IRS line, ME-02 riser sizes and BWIC, is dated 26/10.
Open the draftDrawings on Asite
0 of 3 issued · read-only, synced 09:14
KTY-PEL-ZZ-ZZ-DR-S-2301
Connection details, primary beams to core, gridline C
Planned, nothing issued
KTY-PEL-ZZ-ZZ-DR-S-2302
Connection details, primary beams to core, gridline D
Planned, nothing issued
KTY-PEL-ZZ-ZZ-DR-S-2303
Beam web openings for MEP risers at the core
Planned, nothing issued
Timeline
October 2026
Actions and chases
No action in the minutes and no chase sent on this item.