IRS line · Mechanical and Electrical
ME-02
Riser sizes and builders' work in connection (BWIC)
OpenDue todayDue 26/10Held by NorthvaneDrawings: 0 of 2 issued (from Asite, synced 09:14)
Who is holding it up
Northvane, MEP consultant
“Northvane”
Knock-on effects
ST-03 Steelwork connection details – primary beams to core
Due in 7 days· due 02/11·
Linked items
No linked items.
Chases drafted
To Raj Patel, Northvane
In the chase for RFI-014
RFI-014 / ST-03 / ME-02: thanks for confirming the riser sizes will be with Pellam by Fri 30/10. Mark needs them to finalise the steel connections at the core, due on the IRS on 02/11. Your own IRS line, ME-02 riser sizes and BWIC, is dated 26/10.
Open the draftDrawings on Asite
0 of 2 issued · read-only, synced 09:14
KTY-NVE-ZZ-ZZ-SH-MEP-6202
Core riser sizes schedule
Planned, nothing issued
KTY-NVE-ZZ-ZZ-DR-MEP-6210
Builders' work in connection, core risers
Planned, nothing issued
Timeline
October 2026
Actions and chases
No action in the minutes and no chase sent on this item.