Mon 26 OctKestrel Yard, Marlbridge

Demoweek 1 of 4

Items

IRS line · Mechanical and Electrical

ME-02

Riser sizes and builders' work in connection (BWIC)

OpenDue todayDue 26/10Held by NorthvaneDrawings: 0 of 2 issued (from Asite, synced 09:14)

Who is holding it up

Northvane, MEP consultant

“Northvane”
Information Required Schedule, row 33, Required From · 19/10

Knock-on effects

ST-03 Steelwork connection details – primary beams to core

Due in 7 days· due 02/11·

Linked items

No linked items.

Chases drafted

To Raj Patel, Northvane

In the chase for RFI-014

RFI-014 / ST-03 / ME-02: thanks for confirming the riser sizes will be with Pellam by Fri 30/10. Mark needs them to finalise the steel connections at the core, due on the IRS on 02/11. Your own IRS line, ME-02 riser sizes and BWIC, is dated 26/10.

Open the draft

Drawings on Asite

0 of 2 issued · read-only, synced 09:14

  • KTY-NVE-ZZ-ZZ-SH-MEP-6202

    Core riser sizes schedule

    Planned, nothing issued

  • KTY-NVE-ZZ-ZZ-DR-MEP-6210

    Builders' work in connection, core risers

    Planned, nothing issued

Timeline

October 2026

Actions and chases