RFI · Structural Steelwork
RFI-014
Primary beams at the core: confirm the size and position of penetrations for the MEP risers so the connection details can be finalised (IRS ST-03).
Open5 days lateDue 21/10Held by Northvane
Who is holding it up
Northvane, MEP consultant
“We'll have the riser sizes to Pellam by Fri 30/10.”
Knock-on effects
ST-04 Fabrication drawings for approval
Parent IRS line
ST-03 Steelwork connection details – primary beams to core
Due in 7 days· due 02/11·IRS line
Chases drafted
To Raj Patel, Northvane
RFI-014 / ST-03 / ME-02: thanks for confirming the riser sizes will be with Pellam by Fri 30/10. Mark needs them to finalise the steel connections at the core, due on the IRS on 02/11. Your own IRS line, ME-02 riser sizes and BWIC, is dated 26/10.
Open the draftLast chase sent 20/10
Timeline
Pellam can't finalise the connection details until Northvane sends the riser sizes (). Northvane has said it will send them to Pellam by Fri 30 Oct ().
October 2026
Actions and chases
Action · DTM 07, point 2.1 · Northvane · new · due 23/10
“Steelwork connection details at the core (IRS ST-03, due 02/11) depend on the MEP riser sizes. Northvane to confirm the riser sizes to Pellam.”
Chase sent 20/10 · Tom Ashworth