Mon 26 OctKestrel Yard, Marlbridge

Demoweek 1 of 4

Items

RFI · Structural Steelwork

RFI-014

Primary beams at the core: confirm the size and position of penetrations for the MEP risers so the connection details can be finalised (IRS ST-03).

Open5 days lateDue 21/10Held by Northvane

Who is holding it up

Northvane, MEP consultant

“We'll have the riser sizes to Pellam by Fri 30/10.”
Raj Patel, Northvane · 21/10

Knock-on effects

ST-04 Fabrication drawings for approval

Parent IRS line

ST-03 Steelwork connection details – primary beams to core

Due in 7 days· due 02/11·IRS line

Chases drafted

To Raj Patel, Northvane

RFI-014 / ST-03 / ME-02: thanks for confirming the riser sizes will be with Pellam by Fri 30/10. Mark needs them to finalise the steel connections at the core, due on the IRS on 02/11. Your own IRS line, ME-02 riser sizes and BWIC, is dated 26/10.

Open the draft

Last chase sent 20/10

Timeline

AI summary

Pellam can't finalise the connection details until Northvane sends the riser sizes (). Northvane has said it will send them to Pellam by Fri 30 Oct ().

October 2026

Actions and chases

  • Action · DTM 07, point 2.1 · Northvane · new · due 23/10

    “Steelwork connection details at the core (IRS ST-03, due 02/11) depend on the MEP riser sizes. Northvane to confirm the riser sizes to Pellam.”

  • Chase sent 20/10 · Tom Ashworth

    “Mark can't finalise the steel connections at the core without your riser sizes”