Design Team Meeting No. 07

Download the original
Project
Kestrel Yard, Marlbridge
Date
Wednesday 14 October 2026, 10:00
Venue
Site cabin, Kestrel Yard
Minutes by
Tom Ashworth (TA)
Issued
15/10/2026

Attendees

  • Tom Ashworth (TA), Halbrook Construction Ltd
  • Priya Nair (PN), Halbrook Construction Ltd
  • Daniel Okafor (DO), Farrow Lune Architects
  • Mark Ellison (ME), Pellam Structures
  • Raj Patel (RP), Northvane Engineering
  • Søren Madsen (SM), Velmore Façades
  • Jamie Walsh (JW), Corvane Steel Ltd
  • Helen Doyle (HD), Wrenfield Living Ltd
  • Martin Kerr (MK), Ostley Cost Consultants · Apologies

Key: new actions in green; overdue actions in red; actions closed since the last meeting are struck through and removed at the next.

Minutes

Each point as written, in their numbering and colours; what Buildisy linked or proposed from it beneath.

1. Previous minutes and actions

  • No.1.1Minutes of DTM 06 agreed as a true record.ActionDueLinked toNot linked
  • No.1.2Velmore to confirm curtain wall mullion spacing to suit the flat layouts (RFI-007).ActionVelmoreDue30/09Linked toRFI-007AI-linked

2. Structure

  • No.2.1Steelwork connection details at the core (IRS ST-03, due 02/11) depend on the MEP riser sizes. Northvane to confirm the riser sizes to Pellam.ActionNorthvaneDue23/10Linked toRFI-014AI-linked
  • No.2.2Balcony thermal break at the 2.1 m cantilevers (RFI-022): Pellam reviewing; a heavier unit is likely.ActionPellamDue19/10Linked toRFI-022AI-linked
  • No.2.3Soldier course above the shopfronts (RFI-012): blend B on a stainless support angle agreed in principle. Farrow Lune to issue the drawing.ActionFarrow LuneDue21/10Linked toRFI-012AI-linked

3. Façade

  • No.3.1Brick, panel and mortar specification (IRS FA-02): preliminary issue only. Final specification to follow the sample panel.ActionFarrow LuneDue12/10Linked toFA-02AI-linked
  • No.3.2Farrow Lune's proposal to change the spandrel panel finish on elevations A and C is with the client for review.ActionDueLinked toFA-02AI-linked
  • No.3.3Velmore confirmed the curtain wall programme is unchanged.ActionDueFaçade package

4. Mechanical and electrical

  • No.4.1MVHR units clash with the storage cupboards in type B flats (RFI-020). Northvane to revise the layout.ActionNorthvaneDue21/10Linked toRFI-020AI-linked
  • No.4.2Sprinkler design not required: mist system to the flats by a specialist (IRS ME-04).ActionDueLinked toME-04AI-linked

5. Client

  • No.5.1Use of retail unit 2 (RFI-016): Wrenfield to confirm whether it will be let as a café.ActionWrenfieldDue21/10Linked toRFI-016AI-linked

6. Any other business

  • No.6.1Next meeting: DTM 08, Wednesday 28 October at 10:00, site cabin.ActionDueLinked toNot linked