Halbrook Construction Ltd

Kestrel Yard, Marlbridge – Information Required Schedule

Design Manager: Tom Ashworth · Issue date: 19/10/2026

ABCDEFHIJ
Row in your file
Package
IRS Ref
Information Required
Required From
Date Required
Date Received
Status
Days Late
Comments
6Concrete Frame and Core
7FrameFR-01Core GA drawings and sectionsPellam Structures07/09/202604/09/2026Issued
8FrameFR-02Core wall reinforcement details, levels 00–03Pellam21/09/202625/09/2026Rec'dRec'd 4 days late – no impact on pour sequence. TA
9FrameFR-03Lift pit and sump detailsPS05/10/202605/10/2026Issued
10FrameFR-04Slab edge details and cast-in items, levels 04–08Pellam Structures30/11/20260
12Structural Steelwork
13SteelworkST-01Steel frame GA drawings, levels 01–08Pellam Structures14/09/202611/09/2026Issued
14SteelworkST-02Member sizes and sections schedulePellam28/09/202630/09/2026Rec'd
15SteelworkST-03Steelwork connection details – primary beams to corePellam Structures02/11/2026O/S0SE needs MEP riser sizes first – see RFI-014. TA 16/10
16SteelworkST-04Fabrication drawings for approvalCorvane Steel30/11/20260Corvane can't start until ST-03 is issued
17SteelworkST-05Erection method statement and sequenceCorvaneTBCTBC
18Façade
19FaçadeFA-01Façade elevations and bay studiesFarrow Lune21/09/202618/09/2026Issued
20FaçadeFA-02Brick, panel and mortar specificationFLA12/10/2026prelim 12/10PrelimPreliminary spec only. Final after sample panel sign-off – DO to confirm date
21FaçadeFA-03Window and curtain wall interface detailsVelmore Façades23/11/2026Outstanding0
22FaçadeFA-04Bracket and fixing design calculationsVelmoreStage 4TBC
23Roofing
24RoofRF-01Roof plan, falls and outletsFarrow Lune05/10/202602/10/2026Rec'd
25RoofRF-02Parapet and coping detailsFLAw/c 30/11
26RoofRF-03Roof plant loadings and support positionsNorthvane12/10/202609/10/2026Rev C01 issued
27Balconies and Balustrades
28BalconiesBA-01Balcony support steel and thermal break detailsPellam16/10/202616/10/2026issued
29BalconiesBA-02Balustrade design and fixing details (metal, powder-coated)Farrow Lune30/11/20260
30BalconiesBA-03Balcony drainage and soffit detailsFLATBCTBC
31Mechanical and Electrical
32M&EME-01Services strategy and riser layoutsNorthvane Engineering14/09/202614/09/2026Issued
33M&EME-02Riser sizes and builders' work in connection (BWIC)Northvane26/10/2026O/S0Needed by Pellam for ST-03 connections
34M&EME-03Below-ground drainage layoutsNE12/10/202609/10/2026Rec'd
35M&EME-04Sprinkler designNorthvaneNot req'dMist system to flats by specialist – not in Northvane's scope
37Retail Shell and Residential Fit-out
38Fit-outFO-01Retail unit shell specificationFarrow Lune28/09/202628/09/2026Issued
39Fit-outFO-02Kitchen and bathroom layouts – typical flat typesFLA07/12/202615/10/2026
Part rec'd
Types A–C rec'd; type D outstanding
40Fit-outFO-03Flat entrance door schedule and ironmongeryFarrow Lune14/12/20260