Halbrook Construction Ltd
Kestrel Yard, Marlbridge – Information Required Schedule
Design Manager: Tom Ashworth · Issue date: 19/10/2026
| A | B | C | D | E | F | H | I | J | |
|---|---|---|---|---|---|---|---|---|---|
| Row in your file | Package | IRS Ref | Information Required | Required From | Date Required | Date Received | Status | Days Late | Comments |
| 6 | Concrete Frame and Core | ||||||||
| 7 | Frame | FR-01 | Core GA drawings and sections | Pellam Structures | 07/09/2026 | 04/09/2026 | Issued | ||
| 8 | Frame | FR-02 | Core wall reinforcement details, levels 00–03 | Pellam | 21/09/2026 | 25/09/2026 | Rec'd | Rec'd 4 days late – no impact on pour sequence. TA | |
| 9 | Frame | FR-03 | Lift pit and sump details | PS | 05/10/2026 | 05/10/2026 | Issued | ||
| 10 | Frame | FR-04 | Slab edge details and cast-in items, levels 04–08 | Pellam Structures | 30/11/2026 | 0 | |||
| 12 | Structural Steelwork | ||||||||
| 13 | Steelwork | ST-01 | Steel frame GA drawings, levels 01–08 | Pellam Structures | 14/09/2026 | 11/09/2026 | Issued | ||
| 14 | Steelwork | ST-02 | Member sizes and sections schedule | Pellam | 28/09/2026 | 30/09/2026 | Rec'd | ||
| 15 | Steelwork | ST-03 | Steelwork connection details – primary beams to core | Pellam Structures | 02/11/2026 | O/S | 0 | SE needs MEP riser sizes first – see RFI-014. TA 16/10 | |
| 16 | Steelwork | ST-04 | Fabrication drawings for approval | Corvane Steel | 30/11/2026 | 0 | Corvane can't start until ST-03 is issued | ||
| 17 | Steelwork | ST-05 | Erection method statement and sequence | Corvane | TBC | TBC | |||
| 18 | Façade | ||||||||
| 19 | Façade | FA-01 | Façade elevations and bay studies | Farrow Lune | 21/09/2026 | 18/09/2026 | Issued | ||
| 20 | Façade | FA-02 | Brick, panel and mortar specification | FLA | 12/10/2026 | prelim 12/10 | Prelim | Preliminary spec only. Final after sample panel sign-off – DO to confirm date | |
| 21 | Façade | FA-03 | Window and curtain wall interface details | Velmore Façades | 23/11/2026 | Outstanding | 0 | ||
| 22 | Façade | FA-04 | Bracket and fixing design calculations | Velmore | Stage 4 | TBC | |||
| 23 | Roofing | ||||||||
| 24 | Roof | RF-01 | Roof plan, falls and outlets | Farrow Lune | 05/10/2026 | 02/10/2026 | Rec'd | ||
| 25 | Roof | RF-02 | Parapet and coping details | FLA | w/c 30/11 | ||||
| 26 | Roof | RF-03 | Roof plant loadings and support positions | Northvane | 12/10/2026 | 09/10/2026 | Rev C01 issued | ||
| 27 | Balconies and Balustrades | ||||||||
| 28 | Balconies | BA-01 | Balcony support steel and thermal break details | Pellam | 16/10/2026 | 16/10/2026 | issued | ||
| 29 | Balconies | BA-02 | Balustrade design and fixing details (metal, powder-coated) | Farrow Lune | 30/11/2026 | 0 | |||
| 30 | Balconies | BA-03 | Balcony drainage and soffit details | FLA | TBC | TBC | |||
| 31 | Mechanical and Electrical | ||||||||
| 32 | M&E | ME-01 | Services strategy and riser layouts | Northvane Engineering | 14/09/2026 | 14/09/2026 | Issued | ||
| 33 | M&E | ME-02 | Riser sizes and builders' work in connection (BWIC) | Northvane | 26/10/2026 | O/S | 0 | Needed by Pellam for ST-03 connections | |
| 34 | M&E | ME-03 | Below-ground drainage layouts | NE | 12/10/2026 | 09/10/2026 | Rec'd | ||
| 35 | M&E | ME-04 | Sprinkler design | Northvane | Not req'd | Mist system to flats by specialist – not in Northvane's scope | |||
| 37 | Retail Shell and Residential Fit-out | ||||||||
| 38 | Fit-out | FO-01 | Retail unit shell specification | Farrow Lune | 28/09/2026 | 28/09/2026 | Issued | ||
| 39 | Fit-out | FO-02 | Kitchen and bathroom layouts – typical flat types | FLA | 07/12/2026 | 15/10/2026 | Part rec'd | Types A–C rec'd; type D outstanding | |
| 40 | Fit-out | FO-03 | Flat entrance door schedule and ironmongery | Farrow Lune | 14/12/2026 | 0 | |||